TCN states that the national grid experienced a partial disturbance at about 1;52 pm today, 5th November 2024.
This followed a series of lines and generators tripping that caused instability of the grid and, consequently, the partial disturbance of the system. The data from the National Control Centre (NCC) revealed that a part of the grid was not affected by the bulk power disruption. TCN engineers are already working to quickly restore bulk power supply to the states affected by the partial disturbance.
Presently, bulk power supply has been restored to Abuja, at 2.49pm, and we are gradually restoring to other parts of the country.
We sincerely apologize for every inconvenience this may cause our electricity customers as Ndidi Mbah GM, (Public Affairs) stated
few hours ago today (5/11/24)
Meanwhile tcn has also put out a public notice concerning maintenance in ondo. They released a statement an hour ago stating
TCN TO CARRY OUT MAINTENANCE ON 132kV IFE/ONDO TRANSMISSION LINE
The Transmission Company of Nigeria (TCN) notifies the public that there will be a planned preventive maintenance on the Ife-Ondo 132kV transmission line on Wednesday, November 6, 2024, from 9 am to 4 pm.
The exercise is necessary to enable TCN Lines Maintenance Engineers carry out trace maintenance between Towers 6 and 12.
Consequently, Benin DisCo will not be able to offtake electricity to customers on the Ondo and Okitipupa 33kV feeders.
Bulk power supply will be restored immediately upon completion of the maintenance.